Week 1

Title: General Meeting


Date:09.03.2019


Place:Marketplace


Attendance:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • We decided to meet on campus every Friday.
  • We arranged a meeting with Prof. Jones.
  • We went over new process flow, pointed out challenging parts of the project.
  • We looked into software architecture.
  • Source code is reviewed.

Problems: No problems.


TO-DO:

  • Inspect the source code in detail.
  • Research about asp.Net, vb.net, RTCI systems, jquery, bootstrap, C#, MQS
  • Start building RTCI intake form.
  • Install required software, get familiar.
  • Arrange meeting with NYSBDC staff.
  • Split work between members.

Week 2

Title:Week 2


Date:09.08.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • We met with Prof.Jones and discussed about project details.
  • We researched Internet Informations Systems(IIS) features and how it handle web requests.
  • Set up IIS.
  • Examined IIS manager.

Problems:

  • No problem occured at this week.

TO-DO:

  • Detailed research about web-servers and website development with ASP.NET MVC


Week 3

Title:Week 3


Date:09.15.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • We set up and got familiar with Microsoft Visual Studio.
  • Started to develop a Web Application in ASP.NET.
  • Realized difference between local IIS and IIS express.

Problems:

  • HTML file only accessible when it is shared to every user. Issues with authorization.

TO-DO:

  • Meet with Prof.Jones.
  • Improve C# and ASP.NET skills


Week 4

Title:Week 4


Date:09.22.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Better understanding in MVC.
  • Learned ActionResult tips and helper methods.
  • Understanding how routes are designed.
  • Learned how to rewrite our URL and transfer data from controller to view.

Problems:

  • No problem occured this week.

TO-DO:

  • Meet with Prof.Jones this Thursday and discuss about the progress .
  • Create database and Asp.Net Entity Framework Database Operations.
  • Learn more about Jquery and Client/Server side validation.
  • Make research about authentication and authorization operations.


Week 5

Title:Week 5


Date:09.29.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Met with Prof.Jones this Thursday and discuss about the progress.
  • Searched about the education softwares.
  • Figured out that how the text message and video call should be.
  • Searched about Skype for Business Server 2019.

Problems:

  • No problem occured this week.

TO-DO:

  • Decide if we need to use MVC or not for this project.
  • Make transition from research to practice.


Week 6

Title:Week 6


Date:10.06.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Getting familiar with Skype for Business Server 2019 using the docs.
  • Implementing the code by referencing last years SDBC team's documentation.

Problems:

  • No problem occured this week.

TO-DO:

  • Decide if we need to use MVC or not for this project.
  • Meet with Prof. Jones for further instructions on remote server.

Week 7

Title:Week 7


Date:10.13.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Problems:

  • Prerequisites to install Skype for Business are not met. We require Windows Education or Pro.

TO-DO:

  • Meet with Prof. Jones for further instructions on remote server.

NOTES FROM MEETING

  • Run last years html file on our system
  • Fill the form and store the data.
  • Research best methods to video chat and text chat using IIS.
  • Make a plan and e-mail it to Mr. Jones
  • FTP the file to remote machine

Week 8

Title:Week 8


Date:10.13.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Problems:

  • Prerequisites to install Skype for Business are not met. We require Windows Education or Pro.

TO-DO:

  • Meet with Prof. Jones for further instructions on remote server.

NOTES FROM MEETING

  • Run last years html file on our system
  • Fill the form and store the data.
  • Research best methods to video chat and text chat using IIS.
  • Make a plan and e-mail it to Mr. Jones
  • FTP the file to remote machine

Week 9

Title:Week 9


Date:10.16.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • We made a plan how to improve project.
  • We decided on deliverables until the next meeting.

Problems:

  • IIS gives default web site even though we changed it with the new website.
  • We will continue to implement on Visual Studio for now.

TO-DO:

  • Implement the code for textchat.
  • Configure DNS settings.
  • Figure out how to do video chat by using Skype for business.

Week 10

Title:Week 10


Date:10.27.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • To apply real-time textchat, we examined what we can use and found out that ASP.NET Core SignalR.
  • Applied a web project that enables to send messages from several tabs on a browser.
  • Created a HTML file for textchat page of SBDC website.

Problems:

  • Errors related to our HTML and JavaScript code but we fixed them.
  • We are not able to use remote desktop connection.

TO-DO:

  • Fix remote desktop connection problems.
  • Integrate the web project that we created as a prototype with SBDC project goals.



Week 11

Title:Week 11


Date:11.03.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Made a search about features of Microsoft SQL Server and how to create database in it.
  • Downloaded Microsoft SQL Server Management Studio.
  • Started to create a database that holds informations about clients.
  • Started integrate the web project that we created as a prototype with SBDC project goals.



Problems:

  • Problem about remote desktop connection continuous.

TO-DO:

  • Fix remote desktop connection problems.
  • Complete database and connect to project.




Week 12

Title:Week 12


Date:11.11.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Created a Microsoft SQL Server and connect it to SignalR project.
  • SignalR project is now MVC.
  • Found out IIS is working but not very well.

Problems:

  • Problem about remote desktop connection continuous.
  • IIS is not working efficiently except Prof. Jones' computer.

TO-DO:

  • Fix remote desktop connection problems.
  • Until then create a project that can be deployed using Prof. Jones' remote connection.

Week 13

Title:Week 13


Date:11.17.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Reorganized the HTML file with adding features that is asking more information such as client e-mail address, region and e-mail subject.
  • Searched about the problem with IIS and found out that it may caused by IIS cache.

Problems:

  • Remote desktop connection problems.
  • IIS is not working efficiently except Prof. Jones' computer.

TO-DO:

  • Fix remote desktop connection problems.
  • Try to clear cache on IIS.
  • Meeting with Prof. Jones November 21,Thursday
  • Keep developing the project that can be deployed using Prof. Jones' remote connection.

Week 14

Title:Week 14


Date:11.24.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Developed an form as client intake emailer that enables advisor to send email to client .
  • Created a client information table which consists of form information entered by the user in the beginning.
  • Searched about JavaScript,Bootstrap,CSS and jQuery.
  • Analyzed the code we have as default and made a mind map about how we can deploy our HTML file to this code.

Problems:

  • Remote desktop connection problems.

TO-DO:

  • Keep developing to demo of the SBDC website.
  • Prepare a presentation for final meeting.

Week 15

Title:Week 15


Date:12.01.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Keep developing to demo of the SBDC website.
  • Evaluate what we have learned.
  • Start to preparation for final meeting.

Problems:

  • Remote desktop connection problems.
  • Problems with deployment.

TO-DO:

  • Final meeting presentation.

Week 16

Title:Week 16


Date:16.01.2019


Attendence:Ozden Ertan, Yagmur Egilmez


Accomplishments:

  • Keep developing to demo of the SBDC website.
  • Submit button after filling the form.
  • Save form into database.

Problems:

  • Problems with remote machine storage

TO-DO:

  • Final meeting presentation.