Galorath Project
10/18/2010
We communicated each other on skype. Mr. Lee mentioned about our project. We will use Monte Carlo Analysis.
10/25/2010
We talked about requirements and interface of the project. Mr. Lee mentioned about how we implement monte carlo analysis to the project. We talked about improvement step of our project (Collaboration - Elaboration - Coding - Testing)
11/08/2010
We chose to use WinForms because WPA has less documents and newer than Windows Form. We decided to use Subversion. The Graph API program that we are going to use is Telerik.
We selected our group leader (Mehmet Talha Ugur) and group scheduler(Murat Can Arigun) but it changes on each month.
We did division of labor for reading and exploring documents from internet.
GUI : Mehmet Talha Ugur Graph API : Murat Can Arigun Data Structures – Algorithm : Alp Turgut - Huseyin Aygan Subversion : Ismail Maden
11/17/2010
We talked about gantt chart. We decided milestones of our project. Process Step: Agile software development method Inception : 10.18.2010 - 12.18.2010 Elaboration : 12.18.2010 - 01.24.2011 Collaboration : 01.24.2011 - 03.30.2011 Transition : 03.30.2011 - 05.01.2011
11/22/2010
Each member will explore about Agile Software Development on internet. We are going to conclude DFD and UML between December 18th - January 24th. Gantt Chart is going to be sent to Mr. Fischman until Wednesday. We did our division of labor for our project presentation.