ValuAg - Yucel, Aral ; Sahin, Hamza ; Ak, Birkan ; Atasoy, Kerem
From CS486wiki
Week 1
Date: 2/22/2021
Attandence: Hamza Sahin, Aral Yucel, Kerem Atasoy, Birkan Ak
Accomplishments:
- We got our CPT Approvals - We understood that we have to take action for AOP. - Our first meeting took place with Merwyn.
Problems:
- No problems this week.
To-Do:
- Conduct meeting with Valuag and Action for Older People.
Week 2
Date: 3/1/2021
Attandence: Hamza Sahin, Aral Yucel, Kerem Atasoy, Birkan Ak
Accomplishments:
- Conducted meeting with Valuag and Action for Older People. - Created 4 EC2 Instances, 2 for ValuAg and 2 for AOP, they installed wordpress to each. - Created 2 S3 buckets for each projects, code and media. - Instantiated RDS. - Connected EC2's, S3's and RDS's. - Tested synchronization.
Problems:
- No problems this week.
To-Do:
- Continue working on websites. - Include brand related material. - Conduct meeting with Jim.
Week 3
Date: 3/8/2021
Attandence: Hamza Sahin, Aral Yucel, Kerem Atasoy, Birkan Ak
Accomplishments:
- We added all the products that Jim provided to ValuAg website. - We included every information on the document for AOP. Our AOP web site layout is ready. - We figured out the problem in Prod - Dev system. - We prepared a PowerPoint presentation to explain our problems for the meeting.
Problems:
- We had difficult time while trying to create Dev - Prod environment because of the Database. - Since all the data is sent to databases it is impossible to create the Prod - Dev system with Wordpress.
To-Do:
- According to the response from Jim we will figure out which option we are going to do. - According to feedbacks for AOP website we can change our design.
Week 4
Date: 3/15/2021
Attandence: Hamza Sahin, Aral Yucel, Kerem Atasoy, Birkan Ak
Accomplishments:
- We deleted unnecessary ec2 instance. It cause some problems in current ec2 instance because of common points of the ec2 instances. - We created new ec2 instance and deleted AOP related information. - We created bigger logo - We mockup a calendar and donate ($ amount at the cart) page. - We changed staff members
Problems:
- There was a problem in our previous instance because of common database usage with deleted ec2 instance. We figured out and created new one - We tried to change page links with buttons but our theme did not allow us to change them
To-Do:
- According to the response from Jim and AgeOn office we will make updates in our website.
Week 5
Date: 3/22/2021
Attandence: Hamza Sahin, Aral Yucel, Kerem Atasoy, Birkan Ak
Accomplishments:
- From wordpresses admin pannel we enter css code of the theme that we are using and did multiple changes to make the AgeOn site much better. - We changed the Logo size. Also resized the fonts of our pages to come up with a consistent look. - We made the nav bar buttons seem clickable to add more ease for users. - We made some changes on Related links and Board of Directors pages.
Problems:
- Unfortunately Jim could not attend the meeting and also Lisa so we did not know what we need to change more about the site.
To-Do:
- We will have a meeting with Merwyn and Jim and we will talk about future needs for AgeOn website. Merwyn will inform us about Lisa's needs for the website.